Introduction of POSCO-TCS
2016.08
Completion Ceremony
2016.06
Acquired the plant operation license from IEAT allowing for the commencement of commercial production
2016.06
Hot Run
2016.03
Cold Run
2015.12
Each facility was individually tested
2015.11
All required utilities for plant operation had been secured
2014.10
Ground-breaking Ceremony
2014.09
The ratification for EIA was received from ONEP
2014.08
Contracts for procurement and construction were concluded with
POSCO family companies;
POSCO E&C, POSCO ICT, and POSCO Engineering
2014.06
Permission for investment was granted by the BOI
2014.06
Land usage permission was achieved from IEAT
2014.03
A purchase agreement for the plant site of 260,000 square meter was made with Amata City Industrial Estate
2013.11
POSCO Coated Steel (Thailand) Co., Ltd. was established